Metro Power Company Limited

Metro Power Company Limited

Metro Power Company Limited (MPCL) established the 50 MW Wind Power Project in Jhimpir, Sindh Pakistan having 20 WTGs of NORDEX Make (each 2.5 MW) with 132 KV interconnection facilities. OMS (Private) Limited was appointed by MPCL as Independent Engineer after the approval of CPPA. All the EPA related commissioning tests were witnessed by OMS team and the project COD was successfully achieved on September 15, 2016. 

  • Testing of the Seller Interconnection Facilities
  • Testing of each WTG before Synchronization
  • WTG Commissioning test
  • Reliability Run Test
  • Anemometry system

Key Facts

Location

Jhimpir – Sindh, Pakistan

OMS Role

Independent Engineer

Period of Implementation

Nov 2015 ~ Sep 2016

Project Cost

125 Million USD