Master Green Energy Limited
Master Green Energy Limited initiated the 50 MW Wind Power Project in Jamshoro, Sindh, Pakistan, featuring 25 Siemens Gamesa WTGs (2.0 MW each) with 132 KV interconnection facilities. OMS (Private) Limited, appointed as Independent Engineer, played a crucial role in witnessing all EPA-related commissioning tests, leading to the successful achievement of the project COD on August 21, 2021.
- Testing of Seller Interconnection Facilities
- Testing of each WTG before Synchronization
- WTG Commissioning test
- Reliability Run Test
Key Facts
Location
Jamshoro – Sindh, Pakistan
OMS Role
Independent Engineer
Period of Implementation
September 2020 ~ August 2021
Project Cost
78 million USD