Metro Wind Power Limited
Metro Wind Power Limited (MWPL) established the 60 MW Wind Power Project in Jhimpir, Sindh Pakistan having 30 WTGs of Siemens Gamesa Make (each 2.0 MW) with 132 KV interconnection facilities.
OMS (Private) Limited was appointed by MWPL as Independent Engineer after the approval of CPPA. All the EPA related commissioning tests were witnessed by the OMS team and the project COD was successfully achieved on June 6, 2022.
- Testing of the Seller Interconnection Facilities
- Testing of each WTG before Synchronization
- WTG Commissioning test
- Reliability Run Test
Key Facts
Location
Jhimpir – Sindh, Pakistan
OMS Role
Independent Engineer
Period of Implementation
Aug 2021 ~ June 2022
Project Cost
93 Million USD