Sachal Energy Development Limited (SEDL)
Sachal Energy Development Limited (SEDL) established the 49.5 MW Wind Power Project in Jhimpir, Sindh Pakistan having 33 WTGs of GOLDWND Make (each 1.5 MW) with 132 KV interconnection facilities. OMS (Private) Limited was appointed by SEDL as Independent Engineer after the approval of CPPA. All the EPA related commissioning tests were witnessed by the OMS team and the project COD was successfully achieved on April 11, 2017.
- Testing of the Seller Interconnection Facilities
- Testing of each WTG before Synchronization
- WTG Commissioning test
- Reliability Run Test
- Anemometry System
Key Facts
Location
Jhimpir – Sindh, Pakistan
OMS Role
Independent Engineer
Period of Implementation
Jan 2017 ~ April 2017
Project Cost
134 Million USD