Indus Wind Energy Limited
Indus Wind Energy Limited (IWEL) established the 50 MW Wind Power Project in Jhimpir, Sindh Pakistan having 25 WTGs of General Electric Make (each 2.0 MW) with 132 KV interconnection facilities.
OMS (Private) Limited was appointed by IWEL as Independent Engineer after the approval of CPPA. All the EPA related commissioning tests were witnessed by OMS team and the project COD was successfully achieved on March 20, 2022.
- Testing of the Seller Interconnection Facilities
- Testing of each WTG before Synchronization
- WTG Commissioning test
- Reliability Run Test
Key Facts
Location
Jhimpir – Sindh, Pakistan
OMS Role
Independent Engineer
Period of Implementation
Sep 2021 ~ March 2022
Project Cost
78.5 Million USD